The project
Novello Fund - Construction work on the Minimum Intervention Unit UMI1 of the Novello Fund Social Housing Residential Complex - Quartiere Novello Cesena UMI 2.

Commissioning body

Fabrica Immobiliare SGR S.p.A.

Period

2020
 Quartiere Novello

Activities performed

Upload and drafting of price analyses for all items to the Estimated Bills of Quantities, Chapters:

  • Civil
  • Structures
  • Electrical and special installations
  • Mechanical installations
  • Landscape (external layouts)
  • VVF Facilities (fire-prevention)
  • to determine the economic congruity of the cost estimates drawn up by the Designers.

    R.V.E. Reverse Value Engineering®.

    la rotonda ex magazzini generali
    la rotonda ex magazzini generali

    Sent suppliers

    85

    Received offers

    48

    Percentage / number of receipts

    56%

    R.V.E.® Start date

    02 October 2020

    R.V.E.® End date

    17 December 2020

    Overall number of days

    54
    Importo Progetto

    € 20.124.308,65

    Project Total

    Importo Reverse Value Engineering®

    € 14.727.462,52

    Reverse Value Engineering® Fee

    Reverse Value Engineering® Delta

    € 5.396.846,13